The Three Types of Statutory Party Wall Notices
The Act covers three distinct building scenarios. Serving the correct statutory notice prevents adjoining owners from applying for an emergency court injunction to halt your building works.
Section 1 notices apply when building a new wall directly along or astride the boundary line. Section 2 notices cover structural work to existing shared walls, such as inserting steel padstones or removing chimney breasts. Section 6 notices cover excavations within 3 metres of an adjoining foundation where your dig goes deeper than their footings.
| Notice Type | Statutory Notice Period | Trigger Condition | Standard Outcome with Consent |
| Section 1 (Line of Junction) | 1 Month | Building new wall on boundary line | Proceed with works with zero surveyor fees |
| Section 2 (Party Structure) | 2 Months | Cutting into shared wall for RSJ steels | Schedule of condition completed |
| Section 6 (3-Metre Rule) | 1 Month | Excavating trenches deeper than neighbour | Trial pit data shared and work proceeds |
| Section 6 (6-Metre Rule) | 1 Month | Deep piled foundations within 6m radius | Engineering method statement approved |
- Section 1 Notice: Line of junction; building along or astride boundary line (1 month notice).
- Section 2 Notice: Work on shared party wall or party structure (2 months notice).
- Section 6 Notice: Excavating foundations within 3m or 6m of neighbour's home (1 month notice).
- 14-Day reply window: Neighbours have 14 days to consent, after which a dispute is deemed.
What Happens if Your Neighbour Dissents?
Neighbours frequently dissent to notices out of caution rather than hostility. Dissent does not mean your project is blocked, it simply triggers the appointment of an independent Party Wall surveyor.
Homeowners can agree to appoint one joint 'Agreed Surveyor' to act impartially for both parties, saving substantial costs. If the neighbour insists on appointing their own surveyor, the building owner must pay the reasonable fees of both surveyors.
The Schedule of Condition and Party Wall Award
Before building commences, the appointed surveyor conducts a detailed photographic schedule of condition inspecting the adjoining owner's walls and ceiling plaster.
The resulting Party Wall Award sets working hours, vibration limits, and contractor access terms. If hairline plaster cracks occur during foundation digging, the schedule of condition provides indisputable evidence to resolve damage claims fairly.