| 1. Foundation Excavation | Trench depth, subsoil firmness, tree root heave protection | Before concrete pour | Inspector can demand core drilling or re-digging |
| 2. Oversite & DPC | Damp proof membrane overlap, radon barriers, PIR insulation | Before floor screed pour | Floor must be opened to inspect membranes |
| 3. Structural Steels | Padstone size, steel beam dimensions, bolted connection torque | Before boxing in with plaster | Plasterboard must be stripped away |
| 4. Drainage Testing | 110mm pipe falls, air-pressure water tightness test, soakaway | Before trench backfill | Pipes must be re-excavated for test |
| 5. Final Completion | Emergency egress windows, smoke alarms, handrails, Part L EPC | When building work completes | No Completion Certificate issued |